Replacing Pullman DataCenter Infrastructure, 6/15 and 16

From Saturday, June 15 to Sunday, June 16, 2024, Information Technology Services’ Network Engineering team will replace the Pullman DataCenter infrastructure. Please see the expected maintenance schedule and service impact:

June 15 from 8 a.m. – 5 p.m.

  • ITB and Sloan DataCenters will migrate to the new infrastructure.
  • Impact: Services that rely on the DataCenter infrastructure may experience several small outages.

June 16 from 8 a.m. – 5 p.m.

  • ITB 1010 will migrate to the new infrastructure.
  • Impact: Services that rely on the infrastructure located in ITB 1010 will experience several small outages as cables are moved.
    • ITB 1010 is where some departments house their servers. The departments that have at least some servers in ITB 1010 include: ASIS, CAHNRS, Carson CoB, FAIS, Horticulture, Genomics/Biotech, HRS, Libraries, SESRC, Spokane IT, UCOMM, VCEA (Cybersecurity), and WSU Foundation.

To find more project information and answers to FAQs, please visit the new Pullman DataCenter project webpage.

For questions not answered on the project and FAQ page, please reach out in any of the following ways: