October 2023 Patches

Please see the following Information Technology Services notice:

Date:  10/12/2023

Start Time: 6pm
End Time: Midnight

The following work is being completed:  Installation of Windows patches for Tier 1 servers 

All affected groups:  Pullman campus/Everett campus

Duration of impact:  Patches have synchronized from Microsoft to SCCM.  ITS will be installing patches on Production servers.

All processes affected:  Windows Server Patching – intermittent outages are expected for systems without redundancy.

Follow up steps customers need to take:  None

Contact:  Data Center Operations at 5-0404