Decommissioning MIM Servers, 6/24

Please see the following scheduled Information Technology Services (ITS) maintenance process:

Date: Tuesday, June 24, 2025

Start Time: 12 p.m.

End Time: 1 p.m.

The following work is being completed: ITS is decommissioning the remaining legacy MIM servers and IAM utility servers. These servers supported the legacy MIM synchronization service that ITS replaced during Phase I of the IAM Roadmap.

All affected groups: WSU users utilizing MIM or IAM utility servers

All affected processes: Legacy MIM processes powered by the remaining MIM and IAM utility servers.

Duration of impact: This is a permanent change.

Necessary follow-up steps: None

Questions? Please contact Crimson Service Desk at crimsonservicedesk@wsu.edu or 509-335-4357.