Please see the following scheduled Information Technology Services (ITS) maintenance process:
Start Date: Monday, March 10, 2025
Start Time: 8 p.m.
End Date: Tuesday, March 11, 2025
End Time: 1 a.m.
The following work is being completed: New Kubernetes infrastructure will be deployed. The ESG-Apps, Integration Hub, and Kube-Batch services will be unavailable. This includes Notices.
All affected processes: The following applications will be impacted by this upgrade:
- Kubernetes
- esg-apps-notices
- esg-apps-canvas-sandbox
- esg-apps-canvas-syllabus
- esg-apps-imaging
- esg-apps-imaging-v3
- esg-apps-checklist
- esg-apps-watson
- Integration Hub
Duration of impact: Service downtime is expected to last up to 5 hours.
Necessary follow-up steps: Validate any client services are functioning properly
Questions? Please contact Crimson Service Desk at crimsonservicedesk@wsu.edu or 509-335-4357.