February 2026 Windows Patches

Please see the following scheduled Information Technology Services (ITS) maintenance process: 

Date:  Thursday, Feb. 12, 2025

Start Time: 6 p.m.

End Time: 11:59 p.m.

The following work is being completed: ITS is installing Windows patches for Tier 1 servers.

All affected groups: WSU Pullman and WSU Everett

All affected processes: Windows Server Patching; intermittent outages are expected for systems without redundancy.

Duration of impact: Patches have synchronized from Microsoft to SCCM.  ITS will be installing patches on Production servers.

Necessary follow-up steps: None

Questions? Please call ITS Data Center Operations at 509-335-0404.