ETRL Switch Upgrade, 9/23

Please see the following scheduled Information Technology Services (ITS) maintenance process:

Date: Wednesday, Sept. 23, 2026

Start Time: 10 p.m.

End Time: 11:59 p.m.

The following work is being completed: The Engineering Teaching/Research Labs (ETRL) entrance network feed switch upgrade originally scheduled for Tuesday, Sept. 22 as part of ITS’ quarterly network maintenance was unsuccessful. This work has been rescheduled to September 23.

All affected groups: ETRL building occupants

All affected processes: Network and VoIP phone connectivity

Duration of impact: Two network outages lasting up to 15 minutes are expected. However, the entire maintenance window is reserved for this work.

Necessary follow-up steps: None

Questions? Please contact Crimson Service Desk at crimsonservicedesk@wsu.edu or 509-335-4357.