Pullman Palo Alto Firewall Upgrade

Please see the following ITS maintenance notification:

Dates: Thursday, March 9, 2023
Start Time: 9:00 PM
End Time: 11:59 PM

The following work is being completed: ITS is upgrading the Pullman Campus Palo Alto firewall to address security and bug fixes.

All affected groups: SLA and ITS VMs in Pullman

Duration of impact: Although no service interruptions are expected, the upgrade involves two failovers between the active and passive firewalls.

All processes affected: The failovers will cause a one- to two-second delay in traffic each time, possibly affecting very sensitive jobs.

Follow up steps customers need to take: None.

Questions? Crimson Service Desk via email at crimsonservicedesk@wsu.edu or phone at 509-335-4357.