Please see the following ITS maintenance notification:
Start Time: 6:00 PM Thursday, February 16, 2023
End Time: 5:00 AM Friday, February 17, 2023
The following work is being completed: Installation of Windows patches for Tier 1 servers.
All affected groups: Pullman campus/Everett campus
All processes affected: Windows Server Patching – intermittent outages are expected for systems without redundancy.
Duration of impact: Patches have synchronized from Microsoft to SCCM. ITS will be installing patches on Production servers.
Follow up steps customers need to take: None.
Questions? If you have questions or concerns, please contact Data Center Operations at 509 335-0404